Lights project
Reimagining the Experience | Breaking New Ground | Scope of project | |
To reimagine and reconstruct Phi Studio’s Still From Here installation within a short timeline for the Quoz Arts Festival in Dubai, while maintaining the original artistic experience but replacing heavy materials like epoxy and concrete for a modular, efficient, and sustainable setup. | The original artwork featured a sand-covered lightbox embedded in a concrete platform outdoors at Noor Riyadh. Relocating Still From Here to an indoor venue required an entirely new approach:
| Project Management Fabrication and Installation Material Innovation Collaborative Artist Support |
Bold Choices, Smart Moves
Bold Choices, Smart Moves
D4-PRO committed to delivering the same immersive experience with the following adjustments:
- Custom Stage Deck: Pre-fabricated modular structures replaced poured concrete, enabling faster assembly and disassembly.
- Innovative Material Use:
- Mild Steel Frames for a sturdy foundation.
- Ply Decking and Ramps for lightweight durability.
- Acrylic Layering (amber and clear sheets) mimicked the illuminated epoxy effect.
- Heavy-Duty Adhesive Vinyl ensured a smooth, seamless finish.
- Enhanced Efficiency: Minimal on-site fabrication, saving valuable time and resources.
Same Magic, New Build
Same Magic, New Build
Through collaboration, ingenuity, and meticulous execution, D4-PRO achieved:
Building Brilliance
Building Brilliance
D4-PRO followed a systematic process to ensure success:
- Pre-Production: Off-site fabrication of modular steel and ply elements.
- Acrylic Innovation: Testing layered acrylic sheets to achieve epoxy-like transparency and light diffusion.
- On-Site Assembly: Modular structures were installed, levelled, and finished efficiently within two days.
- Sand Application: A precise 15mm layer of sand completed the experience.





Results
delete
For Alyn, our delivery management covered all aspects of on-site project execution, from initial logistics to final installation. This involved meticulous project management to coordinate the construction timeline, secure necessary permits, and oversee compliance with Terra Pavilion’s regulations.
We managed vendor relationships, ensured material deliveries were on schedule, and aligned each stage of the build with strict site requirements. By overseeing every detail—from setup logistics to safety protocols and site-specific compliance—we delivered a seamless, on-time installation ready for COP 28.
delete (can't seem to work)
Our delivery management for Alyn encompassed every aspect of on-site execution, starting with initial logistics and extending to the final installation. This included creating and managing a detailed construction timeline, securing necessary permits, and ensuring compliance with Terra Pavilion’s regulations.
Vendor and Material Management
We coordinated closely with vendors, ensuring timely material deliveries and resolving any logistical challenges. Every stage of the build was meticulously aligned with the site’s stringent requirements, maintaining efficiency and precision throughout the process.
Ensuring Seamless Delivery
From setup logistics to safety protocols and site-specific compliance, we oversaw every detail to guarantee a seamless installation. The result was a fully executed, on-time delivery of the project, perfectly prepared for COP 28.